Construction Invoice Template

Download a free construction invoice template for progress billing. List the parts of the job with their contract value and the percent complete, add change orders, and the invoice works out what to bill now and how much retainage is held.

The example is a kitchen remodel, worked out line by line.

The GoKaching team

Download it free

No sign-up and no watermark. Replace the text in [brackets] and you are done.

Kestrel Builders LLC

600 Foundry Way

Columbus, OH 43215

office@kestrelbuilders.example

Invoice 3 (progress billing)

Invoice no.
KB-0092-03
Date
November 20, 2026
Due
December 5, 2026

Bill to

Priya and Tom Calloway

42 Linden Court

Dublin, OH 43017

Terms

Due in 15 days

Contract: kitchen remodel, signed Sept 14, 2026

Invoice lines
DescriptionContractDoneThis invoice
Demolition and disposal$4,000.00100%$0.00
Framing and electrical rough-inBilled before: 60%$12,000.00100%$4,800.00
Plumbing rough-inBilled before: 50%$6,000.00100%$3,000.00
Cabinets and countertops$16,000.0050%$8,000.00
Finish carpentry and paint$4,000.000%$0.00
Change order 1: under-cabinet lighting$1,800.00100%$1,800.00
Total this invoice
$17,600.00
Less retainage, 10%
-$1,760.00
Amount due
$15,840.00
Contract sum to date
$43,800.00
Billed to date, including this invoice
$31,800.00
Balance to finish
$12,000.00
Retainage held to date
$3,180.00

How to pay

Pay by check or ACH. Check payable to Kestrel Builders LLC.

Notes

Retainage of 10% is held until final completion, as set out in the contract.

Example with made-up names and amounts. The download has the same layout with [brackets] to fill in.

A progress billing example, step by step

This is the third invoice on a kitchen remodel. For each part of the job the invoice bills the work done since the last invoice, and a part that is already fully billed shows $0.00.
  1. Demolition and disposal: no new work this period, so $0.00
  2. Framing and electrical rough-in: $12,000.00 × (100% − 60%) = $4,800.00
  3. Plumbing rough-in: $6,000.00 × (100% − 50%) = $3,000.00
  4. Cabinets and countertops: $16,000.00 × (50% − 0%) = $8,000.00
  5. Finish carpentry and paint: no new work this period, so $0.00
  6. Change order 1: under-cabinet lighting: $1,800.00 × (100% − 0%) = $1,800.00
  7. Subtotal: the lines add up to $17,600.00
  8. Retainage held back: 10% of $17,600.00 = $1,760.00
  9. Amount due: $17,600.00 − $1,760.00 = $15,840.00

The box under the totals tells the owner where the job stands: the contract sum with the change order, how much has been billed in all, what is left to finish and how much retainage is being held.

How to fill in the construction invoice template

  1. List the parts of the job as in your contract, each with its contract value. Add change orders as their own lines.
  2. Enter the percent complete for each part: what was billed before and what is done to date. The template bills the difference.
  3. Set the retainage to the percentage in your contract. The amount held is taken off the total, and the invoice states it in the notes.
  4. Number the invoice in the series (here “Invoice 3”), and state the date and the payment terms from the contract.
  5. Send it with what the contract asks for, such as photos of the progress or a signed approval from the owner.

Billing for retainage and change orders

Retainage is held back from each payment and released when the work is finished. Show it on every invoice so both sides can follow the running total. The amount you will be paid now is the total, minus the retainage on this invoice.

Change orders are extra work agreed after the contract was signed. Give each one its own line and number, and write it into the contract sum, so the balance to finish stays right.

Frequently asked questions

What is progress billing?

Progress billing means you invoice a large job in stages, as the work gets done, instead of once at the end. Each invoice bills the share of the contract that was completed since the last one.

What is retainage?

Retainage is a percentage of each payment that the owner holds back until the work is finished, as the contract says. In the example it is 10% of each invoice, and the invoice shows how much has been held so far.

How do I bill a change order?

Add the change order as its own line with its own contract value, and say which change order it is. In the example, change order 1 adds $1,800 and raises the contract sum to $43,800.

What is the difference between this and the AIA forms?

This is a simple invoice built on the same idea. On larger commercial jobs the owner or lender may ask for the AIA G702 and G703 forms instead, so ask before you start.

Do I need construction billing software?

For a few jobs a template like this is enough. If you bill many jobs on a schedule, an online invoicing tool saves you from retyping the same lines. GoKaching creates invoices and payment links; it is not a construction management suite.

Create a construction invoice online

Bill each stage of the job from one place and let the totals work themselves out. The client can pay through a link on the invoice.
Create a construction invoice

Send it with GoKaching. Free.

Invoices, quotes and e-signatures with a payment link built in. Always free.

In the United States, your clients can pay with

  • Visa
  • Mastercard
  • ACH Direct Debit
  • Apple Pay
  • Google Pay
  • Cash App Pay
Start for free